Environment Minister George Heyman, Premier John Horgan and Energy Minister Michelle Mungall announce decision to proceed with construction of the Site C dam, B.C. legislature library, Dec. 11, 2017. (Ragnar Haagen/Black Press)

Site C dam goes ahead, cost estimate now up to $10.7 billion

Premier John Horgan says Christy Clark left him no other choice

B.C. Premier John Horgan has given the green light to completion of the Site C hydroelectric dam, after B.C. Hydro revised its cost estimate upward by more than $1 billion.

The B.C. NDP cabinet has struggled with the decision, with the project two years in and facing a cost of $4 billion to shut down construction of the third dam on the Peace River and put the site back the way it was.

After hearing from experts for weeks, the government faced an estimate that B.C. Hydro rates are already expected to rise 30 per cent over the next 10 years without the costs of Site C.

If the dam is halted, rates would go up another 12 per cent by 2020 to pay the cost. That translates to an extra $198 per year for an average single-family house.

RELATED: How Christy Clark made Site C unstoppable

When it proceeds, government officials expect the additional rate increase would be 6.5 per cent when the dam goes into service in 2024. B.C. Hydro would likely apply to the B.C. Utilities Commission to “smooth” that rate increase, raising it in smaller steps to pay for the dam.

Horgan blasted the previous B.C. Liberal government for “megaproject mismanagement” that left the NDP government with little choice.

“It’s clear that Site C should never have been started,” Horgan said. “But to cancel it now would add billions to the province’s debt – putting at risk our ability to deliver housing, child care, schools and hospitals across B.C. And that’s a price we’re not willing to pay.”

The risk reserve for Site C has been increased by $700 million to prepare for further costs increases.

B.C. Liberal critic Mike Bernier, MLA for Peace River South, said the project had been studied for a decade and 2,000 families and Peace region businesses have been left with uncertainty while the new government’s review carried on.

B.C. Liberal finance critic Tracy Redies, a former B.C. Hydro board member, said the NDP’s review confirmed that with projected growth in electricity demand, B.C. will need the equivalent of nine Site C dams by 2050.

B.C. Green Party leader Andrew Weaver said proceeding with Site C was a result of the NDP “pandering for votes” by taking $4.7 billion of Port Mann bridge debt onto the government books to cancel bridge tolls.

Now the province can’t afford the $4 billion cost of stopping the dam, and it has two bad policies based on political expediency, Weaver said.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC HydroBC legislatureSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Comments are closed

Just Posted

In photos: Penticton Speedway celebrates opening weekend

Despite having to turn away roughly 700 cars, organizers celebrating a successful weekend of racing

RCMP investigate bear spray assault outside Penticton pub

Two patrons assaulted with bear spray outside Nanaimo Avenue pub

Coalmont woman airlifted after ATV crash

Off-road vehicle swerved to miss oncoming traffic

Summerland campground to provide COVID-safe accommodations for temporary farm-workers

The managed seasonal worker campsite will be located within a separated area of Peach Orchard Municipal Campground

QUIZ: A celebration of dogs

These are the dog days of summer. How much do you know about dogs?

GoFundMe launched for man severely injured in West Kelowna crash

Doctors say it could be 12 months before Tyler Sheriff is able to walk again

Following incident at sea, fishing lodge says it will reopen despite Haida travel ban

QCL reopens July 10, says president; Haida chief councillor describes ‘dangerous’ boating encounter

Lake Country man facing charges after bear mace incident

The 23-year-old man has since been released from police custody

Vehicle incident stalls traffic on Highway 1 east of Salmon Arm

Drive BC reports road closed, assessment underway

NHL says 35 players have tested positive for COVID-19 since June 8

Positive rate for the league is just under 6%

Peachland Farmers’ Market sees good turnout despite challenging times

Unpredictable weather and pandemic concerns aren’t stopping people from enjoying the market

Kelowna cyclist breaks national ‘everesting’ record

Jacob Rubuliak, 17, rode up and down Knox Mountain 38-and-a-half times, the equivalent elevation of Mount Everest

New Mount Revelstoke National Park campground opening July 15

It’s the first campground built in a mountain national park in over half a century

Most Read