Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

RDOS issues 405 building permits in first nine months of 2019

Construction activity higher this year than during same period last year

Voting locations ‘not going to be perfect’ says Elections Canada

The Princeton Legion was a busy place this weekend, as advance polls… Continue reading

Princetons caboose battle pulls back into court

Princeton’s historic caboose rolled back into court last Thursday, with the Vermilion… Continue reading

Kelowna Liberal, Conservative candidates at odds on economic issues

The mortgage stress test and deficit spending were hot topics at an early morning forum

Princeton suffers highest per capita rate of drug deaths: Coroner report

Princeton has suffered the highest number of illicit drug related deaths in… Continue reading

Election 2019: Robert Mellalieu — Green Party candidate for Central Okanagan-Similkameen-Nicola

Robert Mellalieu is running for the Green Party in Central Okanagan-Similkameen-Nicola

North Okanagan patients benefit from new staff and equipment

New physiatrist and much-needed equipment at VJH

Growing cherries, apples, pears — and big pumpkins

Boerboom worked to produce a massive melon from his Summerland farm

West Kelowna resort denies being fined after six bears destroyed

‘We are good with the compliance,’ said the resort’s operations manager

Workshops give North Okanagan businesses a boost

Small Business Week celebrated by Community Futures

Shuswap voter unhappy with polling times that don’t allow him to vote

Resident thinks with technology available polls should be open more days

Ready, aim, fire: Penticton residents invited to shoot exploding pumpkins

The event is hosted by the Penticton Shooting Sports Association on Nov. 2

Police investigating suspicious fire at Airport Inn in Lake Country

Twenty-four firefighters responded to the call around 2 a.m.

Penticton Fire Department says farewell to Cpt. Glenn Beierle

Beierle retired on Oct. 17 following 30 years of service with the department

Most Read