Construction of the 19 km Spuzzum section of the Interior-Lower Mainland transmission line

Merritt-Coquitlam power line completed

A year behind schedule and over-budget, high-voltage line subject to arbitration between BC Hydro and its contractor

A year behind schedule and $18 million over budget, the latest high-voltage line of the BC Hydro grid has been completed from Merritt to Coquitlam.

The new line parallels the existing main line supplying the Lower Mainland and Vancouver Island from hydro dams on the Peace and Columbia Rivers. It was originally to be completed in 2014, but the main contractor fell behind and BC Hydro used its own crews to complete one of the most difficult portions, a 19 km stretch north of Hope.

The final cost for the 247 km line is expected to be $743 million, which Energy Minister Bill Bennett said is about two per cent more than the initial $725 million budget.

“There is an ongoing arbitration between BC Hydro and [contractor] Flatiron Graham as to who’s going to bear the cost of the delay, because the project was delayed by a year,” Bennett said in an interview Friday.

It’s the first 500-kilovolt line added to the BC Hydro grid in 40 years, to keep up with demand from a growing southwestern B.C. population and increase reliability in the event of disasters.

“You always have the potential for a big avalanche or a mudslide, even an earthquake, to take out one or two of your big transmission lines, bringing electricity in from the two rivers, the Columbia and the Peace,” Bennett said.

NDP energy critic Adrian Dix said the project started out with a $600 million estimate, making it $143 million over budget. He said it’s the latest in a series of cost overruns, including the Northwest Transmission Line north of Terrace, the Dawson Creek-Chetwynd line and the Iskut extension in the northwest.

Bennett said BC Hydro is under-budget on its overall capital construction plan, including $100 million under budget on reconstruction of five generating units at the W.A.C. Bennett Dam on the Peace River, and there is no additional effect on rates.

BC Hydro is committed to a capital budget of $2.4 billion a year for the next 10 years, including construction of the Site C dam on the Peace River and reconstruction of the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island.

 

Just Posted

Video: Update one man arrested in Okanagan Falls

The RCMP has requested the school go into lockdown

Okanagan’s first Christmas was cold and bleak

Father Pandosy and his crew likely spent their first Christmas cold and hungry

Meningococcal disease outbreak declared in Okanagan

Five cases in last six months among 15-to-19 year-olds, including one in Coldstream

Holiday Train rolls through the Shuswap

Hundreds of people have gathered in Sicamous, Canoe and Salmon Arm for… Continue reading

Column: Make it a green Christmas

Instead of purchasing a cuddly stuffie this year, put your money towards helping the real thing.

B.C. woman brain injured in crash as a baby gets $1.1 million in damages

Trial heard the woman was 16 months old, being carried by her mother when they were both hit

What’s happening

Find out about the events happening in your community this weekend

Interior Health holding immunization clinic in Vernon Saturday

IH issues list of Okanagan meningococcal immunization clinics

Court denies WestJet’s bid to toss out discrimination lawsuit of former worker

Mandalena Lewis is suing WestJet over allegations of gender-based discrimination

VIDEO: 3 months later, rescued sea lion released back into ocean

The young animal was found in Campbell River three months ago

Sagmoen neighbours recall alleged hammer attack

Woman was screaming outside Maple Ridge townhouse in 2013

One convicted, two cleared in 2014 deaths of men in B.C.’s Cariboo

Andrew Jongbloets convicted of manslaughter in deaths of Matthew Hennigar, 23 and Kalvin Andy, 22

Most Read