Installation of a fifth and sixth generating unit at Mica dam has taken eight years.

Dam expansion done as BC Hydro demand slumps

Four per cent rate increase expected next year to keep up with big maintenance, construction of Site C on the Peace River

BC Hydro has completed one of its mega-projects, expansion of the Mica Dam on the Columbia River to full capacity, as the utility weathers a slump in mining and continued delays in liquefied natural gas projects.

The addition of two water turbines to Mica cost $714 million, plus a new high-voltage transmission line to carry power to the Lower Mainland and Vancouver Island. BC Hydro has also moved up plans to add a sixth turbine at the Revelstoke Dam, as work continues on the Site C project on the Peace River.

[A look inside the Mica Dam project here]

With major upgrades at the Ruskin Dam in the Fraser Valley and the John Hart Dam on Vancouver Island also underway, BC Hydro has applied for a four per cent rate increase to take effect on April 1, 2017. That follows increases of nine and six per cent in the past two years, mainly to finance major projects and pay down debt.

The four per cent rate is a one-year interim application to the B.C. Utilities Commission, which would add about $4 a month to the average residential electricity bill. Faced with mine shutdowns and uncertainty in large LNG projects, BC Hydro put off its three-year rate proposal when it filed the application in February.

Under a 10-year rate plan imposed by the B.C. government, rates are to increase 3.5 per cent in 2018 and three per cent in 2019. After that, authority over rate setting is to return to the BCUC.

Despite the current downturn for industrial customers, BC Hydro projects demand to increase 40 per cent over the next 20 years, due to population and industrial growth.

It has also scheduled major maintenance at Mica, with two original turbines built in the 1970s due to come out of service for 18 months each.

The B.C. government has proposed to Ottawa that a second power grid link to Alberta be built to help that province retire its coal-fired power plants.

 

Just Posted

Video: Update one man arrested in Okanagan Falls

The RCMP has requested the school go into lockdown

Okanagan’s first Christmas was cold and bleak

Father Pandosy and his crew likely spent their first Christmas cold and hungry

Meningococcal disease outbreak declared in Okanagan

Five cases in last six months among 15-to-19 year-olds, including one in Coldstream

Holiday Train rolls through the Shuswap

Hundreds of people have gathered in Sicamous, Canoe and Salmon Arm for… Continue reading

Column: Make it a green Christmas

Instead of purchasing a cuddly stuffie this year, put your money towards helping the real thing.

B.C. woman brain injured in crash as a baby gets $1.1 million in damages

Trial heard the woman was 16 months old, being carried by her mother when they were both hit

What’s happening

Find out about the events happening in your community this weekend

Interior Health holding immunization clinic in Vernon Saturday

IH issues list of Okanagan meningococcal immunization clinics

Court denies WestJet’s bid to toss out discrimination lawsuit of former worker

Mandalena Lewis is suing WestJet over allegations of gender-based discrimination

VIDEO: 3 months later, rescued sea lion released back into ocean

The young animal was found in Campbell River three months ago

Sagmoen neighbours recall alleged hammer attack

Woman was screaming outside Maple Ridge townhouse in 2013

One convicted, two cleared in 2014 deaths of men in B.C.’s Cariboo

Andrew Jongbloets convicted of manslaughter in deaths of Matthew Hennigar, 23 and Kalvin Andy, 22

Most Read