Copper Mountain commissioned new primary crusher

Copper Mountain provides update

Copper Mountain Mining Corporation (TSX: CUM) (the “Company” or “Copper Mountain”) announces that construction work on the Company’s Copper Mountain Project is nearing completion. The Company has now commissioned the new primary crusher and overland conveyor system. Over the past weekend the Company crushed ore which was conveyed to the coarse ore stockpile in preparation of the concentrator start up. The project continues to proceed on schedule and as planned with construction expected to be completed by the end of April 2011, commissioning of equipment is scheduled to occur during May 2011, and full production is scheduled to be achieved by the end of June 2011.The first ore was delivered to the primary crusher over the past weekend and everything went as planned. The Company has been stock piling ore as part of preproduction mining activities. With commissioning of the primary crusher complete, the Company is able to build its crushed ore stock pile in preparation for start up of the concentrator.

Assembly of the second PC 8000 hydraulic shovel has been completed and is being put into service. The two PC 8000 shovels are the main loading units for the mine. A total of 12 out of 13 (240 ton) haul trucks have been assembled and commissioned and are now in operation, with the final 13th haul truck to be assembled by the end of the month.

The PC 8000 shovel’s are performing as expected and are loading the 240 ton trucks to meet our planned mining rate of 160,000 tonnes per day. Pre-production mining activities commenced in the Pit 3 area with the first PC 8000 unit on the western wall and now the second PC 8000 is in operation on the eastern wall push-back. Construction activities within the concentrator are well advanced with most of the work being directed at completion of piping and electrical tasks. Installation of the grinding mills is progressing as planned with pressure testing of hydraulic lube lines and the installation of the SAG liners. The grinding mills are expected to be ready for testing by the end of April. A commissioning team has been established for testing the plant equipment as it is completed by the contractor. The project currently has 520 workers on site, of which 240 are Copper Mountain personnel and the rest associated with the construction activities. At full production, the project will employ 271 personnel.

 

Just Posted

The weekly COVID-19 map for June 6 to 12. (BC CDC)
South Okanagan sees only 5 new cases in last week

The Similkameen Valley went a second week without any new cases

Birtch Parlee is one of approximately 132,000 transgender people living across the nation, according to Statistics Canada. Photo submitted
Transgender in a small town – Princeton B.C.

“I buried it. I pushed it down. I lived a lie.”

A tent housing a mobile vaccination clinic. (Interior Health/Contributed)
Second dose vaccinations accelerating throughout region: Interior Health

To date, more than 675,000 doses have been administered throughout the region

Dan Albas
COLUMN: Reopening the international border

Governments in Canada and the United States are working towards reopening plans for the border

Okanagan Lake (File photo)
Thompson-Okanagan ready to welcome back tourists

The Thompson-Okanagan Tourism Association expects this summer to be a busy one

Bear wanders Kelowna on June 15. (Michelle Wallace/Facebook)
Bear climbs fence, uses crosswalk in Kelowna

The bear was spotted on Baron Road Wednesday evening

Hundreds of people, young and old, joined the three-day Walking Our Spirits Home procession, honouring residential school survivors, those who never made it home and all those affected by the institutions. Here people walk the third portion on June 13. (Martha Wickett - Salmon Arm Observer)
Walking Our Spirits Home from Kamloops provides path to healing

First Nations in and beyond Secwépemc territory join in to honour residential school survivors

More flames
Lake Country home destroyed in large blaze, 11 dogs rescued

Fire crews are responding to 10839 Hallam Drive

(Facebook/Kelowna Cabs)
Kelowna Cabs reaches tentative agreement with dispatchers union

The tentative agreement could help end the dispute between the taxi company and the dispatchers

FILE – A science class at L.A. Matheson Secondary in Surrey, B.C. on March 12, 2021. (Lauren Collins/Surrey Now Leader)
Teachers’ union wants more COVID transmission data as B.C. prepares for back-to-school

BCTF says that details will be important as province works on plan for September

A boat sharing service is extending to Summerland. The company, Penticton Boat Club and Rentals, is also taking over the boat rentals at Summerland Waterfront Resort. (Photo by Chris Stenberg)
Boat sharing service extended from Penticton to Summerland

Company will also operate boat rentals at Summerland Waterfront Resort

201 First Street West 1980s. Prior revitalization. (Photo from Revelstoke Museum and Archives)
Man who redesigned downtown Revelstoke honoured with lifetime achievement award

Robert Inwood has worked on historical projects across the province

Provincial health officer Dr. Bonnie Henry outlines B.C.’s COVID-19 restart plan, May 25, 2021, including larger gatherings and a possible easing of mandatory masks on July 1. (B.C. government photo)
B.C. records 120 new COVID-19 cases, second vaccines accelerating

Lower Pfizer deliveries for early July, Moderna shipments up

The weekly COVID-19 map for June 6 to 12. (BC CDC)
South Okanagan sees only 5 new cases in last week

The Similkameen Valley went a second week without any new cases

Most Read